GST on under-construction apartments explained

Featured Image of GST on under-construction apartments explained


GST on under-construction apartments is a property tax in India that charges 1% on affordable flats and 5% on regular flats without any tax credit. This tax applies only while the building work is still going on before the city gives an Occupancy Certificate (OC) or Completion Certificate (CC). Once a flat gets its final certificate or is ready to move in, you pay zero GST under Schedule III of the tax law. The tax calculation also leaves out one-third (33.33%) of the flat cost for land, which means you only pay tax on the remaining two-thirds of the price for the building work. You pay this tax in parts each time the builder asks for money during construction.

What Is GST on Under-Construction Property and When Does It Apply?


GST on under-construction property is a direct home tax made up of Central GST and State GST that you pay when you buy a house before it gets an Occupancy Certificate.

  • During Construction: You pay this tax on every bill the builder sends you, from digging the ground to building the roof.
  • When It Stops: The tax stops completely the day the city office gives the project a full Completion Certificate or people move in.
  • Ready Homes Pay Zero: If you buy a finished home with an OC in hand, you skip GST entirely and pay only your state stamp duty and registration fee.

GST Tax Slabs on Residential Real Estate: Affordable vs Non-Affordable Housing


The government divides residential flats into two clear groups based on home size and total sale price.

House Type Metro Carpet Area Non-Metro Carpet Area Maximum Price Final GST Rate Tax Credit (ITC)
Affordable Flat Up to 60 sq. m (645 sq. ft.) Up to 90 sq. m (968 sq. ft.) Up to ₹45 Lakhs 1% No
Regular / Luxury Flat Above 60 sq. m Above 90 sq. m Above ₹45 Lakhs 5% No
Shops Inside Housing Projects Up to 15% of total project area Up to 15% of total project area Any price 5% No

To get the low 1% tax rate, your flat must meet both the size limit and stay under the ₹45 Lakh price tag. If your flat is bigger or costs more than ₹45 Lakhs, your tax rate automatically becomes 5%.

How Is GST Calculated on Under-Construction Flats?


The GST calculation on under-construction flats removes a flat 33.33% land cost from your total deal, and then taxes the remaining 66.67% construction work at 7.5%, so your final bill equals exactly 5%.

  • Total Price Check: If your flat costs ₹1,00,00,000 (₹1 Crore), the law first takes away ₹33,33,333 for land cost.
  • Taxable Share: That leaves ₹66,66,667 as the actual building work that gets taxed.
  • Final Tax Amount: Taking 7.5% of ₹66,66,667 gives you ₹5,00,000, which is the exact same as paying 5% on your ₹1 Crore total price.

Input Tax Credit (ITC) Rules and Builder Procurement Mandates


Input Tax Credit rules stop builders from cutting their own tax costs on items like steel and cement, while forcing them to buy mostly from legal tax-paying vendors.

  • No Tax Rebates: Builders cannot claim back the taxes they pay on cement, steel, bricks, or paint to reduce their final tax bill.
  • The 80% Rule: Builders must buy at least 80% of all their building goods and labor from GST-registered sellers.
  • Shortfall Fine: If a builder buys less than 80% from registered sellers, they must pay an 18% penalty tax themselves, and any unregistered cement gets hit with a heavy 28% tax.

Applying 5% GST to Luxury High-Rises: Practical Analysis of Auro Anantha, Raidurg


Auro Anantha is a high-rise luxury project by Auro Realty on Delhi Public School Road in Raidurg, Hyderabad (500008), where every under-construction 4 BHK flat pays a flat 5% GST on the base cost. Built on 3.5 acres of land near HITEC City, the project features 2 towers rising across 4 basements, a ground floor, and 54 upper floors with 368 total flats. Since these pre-launch 4 BHK homes run from 3,600 to 3,800 sq. ft. and start at ₹4.8 Crore, they are well past the ₹45 Lakh limit and fit straight into the 5% tax bracket.

Construction Stage Bill Share Bill Amount (Base: ₹4.8 Cr) 5% GST to Pay
Booking Advance 10% ₹48,00,000 ₹2,40,000
Basement Work (4 Basements) 20% ₹96,00,000 ₹4,80,000
Floor Slabs (54 Floors) 45% ₹2,16,00,000 ₹10,80,000
Walls and Outside Work 15% ₹72,00,000 ₹3,60,000
Pipes and Wiring 5% ₹24,00,000 ₹1,20,000
Possession (Planned Dec 2030) 5% ₹24,00,000 ₹1,20,000
Total Flat Cost 100% ₹4,80,00,000 ₹24,00,000

A homebuyer at Auro Anantha pays ₹24,00,000 in total GST across the construction period before moving in. Covered parking slots in the 4 basements and floor charges carry the same 5% tax when they are written directly into your main flat agreement.

Additional Charges and Ancillary Levies: Parking, Maintenance, and Preferential Location Fees


Extra fees that come with your new flat booking have different tax rates depending on whether they sit inside your main home contract or come on separate bills.

  • Car Parking and Floor Fees: Parking slots and floor-rise charges written inside your main flat agreement count as home construction and take the standard 5% GST rate.
  • Advance Maintenance Fees: Advance upkeep money taken by builders attracts an 18% tax if your monthly maintenance bill is higher than ₹7,500 per flat.
  • Corpus Fund Deposits: Sinking funds and corpus deposits collected for your future resident welfare group do not attract any GST.

Frequently Asked Questions


1. Is GST applicable on ready-to-move-in flats?

GST does not apply to ready-to-move-in flats that have an official Occupancy Certificate (OC) or Completion Certificate (CC) from the local city office. Buyers of ready homes pay only state stamp duty and registration fees, saving the extra 5% tax charged on under-construction flats.

2. Can a buyer claim a GST refund if an under-construction flat booking is cancelled?

A buyer can get their GST money back from the builder if they cancel the booking within the same financial year under Section 34 of the tax law. The builder issues a credit note, fixes the tax in their monthly tax filing, and returns the tax cash to the buyer.

3. Why is land value deducted from the GST calculation on apartments?

Land value is left out of GST because real land is an immovable asset taxed only by state stamp duty laws. The tax board gives a standard one-third (33.33%) discount on the total deal, so you only pay tax on the remaining building work.

5. How does GST apply to maintenance charges paid after possession?

Maintenance charges billed by a registered housing society attract 18% GST only when the monthly fee is more than ₹7,500 per member and the society makes over ₹20 Lakhs a year. If your monthly upkeep stays at or under ₹7,500, you pay zero tax on it.

6. Are resale under-construction flats subject to GST?

Resale under-construction flats attract GST on all remaining milestone payments that the new buyer pays to the builder before the building gets its Occupancy Certificate. The new owner takes over the payment plan and pays the 5% (or 1%) tax on all bills that come due.